The work party for 13th January 2024 consisted of 12 volunteers and carried out 65 hours of work. It was very successful with all of the planned work being satisfactorily completed as follows: Additional unplanned Work: Other points to note:
October 2022 Digger Trial
October 2022 Digger Trial A 5-day work party was held 24-28/10/22 to assess the effect of limited mechanisation on work party productivity. A 0.8t micro digger on hire from L M Plant Hire was used to assist with drainage improvement
October 2022 Work Party
Saturday’s work party, consisting of 12 volunteers doing 90 hours of work on the Dava Way. It was very successful with all the planned work being satisfactorily completed as follows: Undergrowth and trees cut back and removed from the cutting