November 2023 Work Party The work party for 18th November 2023 consisted of 9 volunteers and carried out 72 hours of work at the northern end of the Foxhill cutting, one mile north of Dava and in the woodland area
November 2023 Work Party

November 2023 Work Party The work party for 18th November 2023 consisted of 9 volunteers and carried out 72 hours of work at the northern end of the Foxhill cutting, one mile north of Dava and in the woodland area
Foxhill Cutting Drainage Project The Foxhill Cutting drainage improvement project consisted of 3 days of work with a mechanical micro digger, two days in early September (7th & 8th) and one day in October (6th). The objective of the project
August 2023 Work Party The work party for 12th August 2023 consisted of 11 volunteers and carried out 67 hours of work on the southern end of the Dava Way. It was very successful with most of the planned work
June 2023 Work Party The work party for 10th June 2023 consisted of 10 volunteers and carried out 66 hours of work on the southern and mid sections of the Dava Way in preparation for the Ghost Train Walk on
May 2023 Work Party Saturday’s work party, consisting of 9 volunteers, did 68.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
April 2023 Work Party Saturday’s work party, consisting of 5 volunteers, did 42 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
February 2023 Work Party Saturday’s work party, consisting of 9 volunteers, did 65.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
October 2022 Digger Trial A 5-day work party was held 24-28/10/22 to assess the effect of limited mechanisation on work party productivity. A 0.8t micro digger on hire from L M Plant Hire was used to assist with drainage improvement
Saturday’s work party, consisting of 12 volunteers doing 90 hours of work on the Dava Way. It was very successful with all the planned work being satisfactorily completed as follows: Undergrowth and trees cut back and removed from the cutting
September 2022 Work Party The work party, consisting of 8 volunteers, was very successful and all the planned work was satisfactorily completed as follows: A 60m strip, approximately 1m wide, of mud, organic material and roots was removed from the