August 2024 Work Party The work party for 10th August 2024 consisted of 16 volunteers with over 125 hours of work being carried out. This was the most well attended work party for several years, with some new volunteers coming
May 2024 Work Party
May 2024 Work Party The work party for 11th May 2024 consisted of 8 volunteers and carried out 52.5 hours of work. It was very successful with all of the planned work at the Heatherbells Cutting being completed as follows:
February 2023 Work Party
February 2023 Work Party Saturday’s work party, consisting of 9 volunteers, did 65.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
January 2023 Work Party
January 2023 Work Party Saturday’s work party, consisting of 11 volunteers, did 86.5 hours of work on the Dava Way. It was very successful with all the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work: Other