February 2023 Work Party

Saturday’s work party, consisting of 9 volunteers, did 65.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows:

  • Drainage ditch cleaned of vegetation and organic debris in Aucheon cutting completed.
  • Electronic footfall counter reinstalled at the Dunphail Breathing Place to record cyclist.
  • Path surface work at the Bantrach crossing to create a good path surface around the locked gates.

Additional unplanned Work:

  • 50m of ditching work on east side of the path in the Bantrach cutting to clear a blockage

Other points to note:

  • No injuries or near misses were reported
  • The dumped ditch spoil in the Sluggan Burn borrow pit needs a tidied up with a digger to allow future ditch spoil deposits.