The work party for 13th January 2024 consisted of 12 volunteers and carried out 65 hours of work. It was very successful with all of the planned work being satisfactorily completed as follows: Additional unplanned Work: Other points to note:
December 2023 Work Party
December 2023 Work Party The work party for 9th December 2023 consisted of 12 volunteers and carried out 70 hours of work at the Dallas Dhu Ramp area and at the Rafford Bridge path junction. It was very successful with
November 2023 Work Party
November 2023 Work Party The work party for 18th November 2023 consisted of 9 volunteers and carried out 72 hours of work at the northern end of the Foxhill cutting, one mile north of Dava and in the woodland area
October 2023 Work Party
October 2023 Work Party The work party for 14th Octobert 2023 consisted of 8 volunteers and carried out 47.5 hours of work at the northern end of the Foxhill cutting, one mile north of Dava. It was very successful with
Foxhill Cutting Drainage Project
Foxhill Cutting Drainage Project The Foxhill Cutting drainage improvement project consisted of 3 days of work with a mechanical micro digger, two days in early September (7th & 8th) and one day in October (6th). The objective of the project
August 2023 Work Party
August 2023 Work Party The work party for 12th August 2023 consisted of 11 volunteers and carried out 67 hours of work on the southern end of the Dava Way. It was very successful with most of the planned work
June 2023 Work Party
June 2023 Work Party The work party for 10th June 2023 consisted of 10 volunteers and carried out 66 hours of work on the southern and mid sections of the Dava Way in preparation for the Ghost Train Walk on
May 2023 Work Party
May 2023 Work Party Saturday’s work party, consisting of 9 volunteers, did 68.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
April 2023 Work Party
April 2023 Work Party Saturday’s work party, consisting of 5 volunteers, did 42 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work:
February 2023 Work Party
February 2023 Work Party Saturday’s work party, consisting of 9 volunteers, did 65.5 hours of work on the Dava Way. It was very successful with most of the planned work being satisfactorily completed or progressed as follows: Additional unplanned Work: